After successfully finishing our interview with Mrs. S, we had the chance to manipulate a ROV that was already made, giving us a sense of what it was like and how they were framed. We finished up our guidelines pages by adding some pictures we took, and next time, we will receive our box and officially start our ROV!!



Jennifer rocks safety
googles while soldering
May 9th, 2017
Finished product!
Today we split into three teams and each starting working on our own task. The control and motor building groups mainly worked on the practice activities which were stripping wires and soldering, and the frame building worked on the design of the frames. Most of us finished soldering our practice wires and are ready to waterproof them.




May 11th, 2017
The motor building team completed their practice activity, and moved on to attaching the propellers to the motor. The control box building team helped people out with soldering, and then started on their practice circuit. Lastly, our frame builder and designer recorded the measurements for the frame she had considered making last time, and also created a mini sketch of what it will look like.


May 12th, 2017
Continuing from yesterday, Jennifer and Mana worked on attaching the propellers to the motors, and then finished creating the tether management cross. Cindy worked on coming up with ideas of the frame and measuring out her ideas. Beth finished her practice circuit and then started on the control box.



May 16, 2017
Today, Beth started her control box and finished soldering a few items. Cindy worked on creating the prototype of our ROV, and made measurements along with diagrams. Jennifer and Mana worked on connecting the tether to the motors.

May 18, 2017
Beth was absent today so no progress on the control box:( Cindy worked on completing the prototype of the ROV frame and our design is almost decided! Jennifer and Mana worked on soldering motor wires and tether wires, and then waterproofed them

May 19, 2017
Cindy worked on building her frame today and put holes into them. Beth finished making her control box and soldering the power cord, and Jennifer and Mana finished their motor system. We will be connecting our motor system and control box next time, and then putting it on our frame!